M/S UNITED COAL CARRIER VS RAJASTHAN STATE MINES AND MINERAL LIMITED
- Court
- Rajasthan High Court
- Bench
- Jodhpur
- Date
- 30 Mar 2026
- Citation / case number
- CW / 15655 / 2024
Summary
The petitioner challenged termination of its contract for delayed commencement and deficient performance. HELD- Where a force majeure clause extends to causes beyond the affected party’s reasonable control, persistent third-party obstruction materially preventing performance falls within the clause even if not expressly enumerated. Delay and shortfall caused thereby cannot be attributed to the contractor or justify termination. Petition allowed.