M/S UNITED COAL CARRIER VS RAJASTHAN STATE MINES AND MINERAL LIMITED

Rajasthan High Court · 30 Mar 2026

Open in Nyaya
Court
Rajasthan High Court
Bench
Jodhpur
Date
30 Mar 2026
Citation / case number
CW / 15655 / 2024

Summary

The petitioner challenged termination of its contract for delayed commencement and deficient performance. HELD- Where a force majeure clause extends to causes beyond the affected party’s reasonable control, persistent third-party obstruction materially preventing performance falls within the clause even if not expressly enumerated. Delay and shortfall caused thereby cannot be attributed to the contractor or justify termination. Petition allowed.